S-161 Modification, Upper St Johns River Basin, Jane Green Detention Area

<< Back to Project Samples

J2 was contracted to perform construction services to provide adequate draw down for Jane Green Creek through L-73 in order to decrease hydraulic period upstream in the Bull Creek Wildlife Management Area.  S-161 modifications should nearly restore Jane Green Creek to its historical flow alignment and provide improved draw down through L-73 with an invert of 19.0 feet.

Work included extensive dewatering and drainage control, reconfiguring a weir by removing concrete from ogee weir structure to form two box culverts, adding mechanical slide gates and structural steel access platforms, forming and pouring a new apron slab at the base of the weir, removing existing vertical lift gates and associated machinery, and installing floating debris barriers.  Temporary dewatering berms or structural closure will be needed of facilitate required.

The work covered under this contract included the disassembly, removal, and disposal of gate hoist equipment that was coated by paint having a lead-base primer. This equipment was disassembled and removed in a manner which did not expose any employee to lead at or above the action level of 29 CFR 1926.62. The removed equipment was disposed of in accordance with applicable federal, state and local regulations.  The newly constructed culverts were painted with an Epoxy coating that required unique safety measures in the semi-confined space the work was performed within.  This paint was applied in a manner which did not expose any employee to OSHA controlled substances at or above the action level of 29 CFR 1926.

The project's contract duration fell largely during the rainy season, and the specific location of the work to be performed presented unique challenges that had to be overcome through careful consideration and diligent efforts.  The work involved in the Jane Green Det. Project was situated below the natural water table and at the bottleneck of an ecologic drainage system.  As the rains continually fell during the project, rapidly rising water levels on both upstream and downstream sides of the dewatered work zone threatened the success of the project.  Also, continual rain washouts destroyed construction progress and degraded haul routes.  Project management assessed and solved these issues by dedicating a portion of the work day each and every day to perform maintenance on dewatering structures as well as haul routes.  On-site management performed daily evaluations of site conditions and the resultant schedule delays.  These daily evaluations were taken into consideration and on-site management made on the fly changes in work schedule and priorities, as well as scheduled material deliveries to the site to keep the project running on schedule.  These daily considerations and regulations made it possible for this project to be completed successfully and on-time.


 

S-161 Modification, Upper St Johns River Basin, Jane Green Detention Area

S-161 Modification, Upper St Johns River Basin, Jane Green Detention Area



Back to Top